Case Studies: Return to Case Studies Index 53,000 sq ft R&D TI in Sunnyvale, CA Goal - deliver complete interior upgrade while spending less than $10 a square foot on capitalized improvements Completed - July 2004 Project Responsibilities - complete project management of interior construction including, electrical, HVAC, carpentry, security infrastructure, furniture and fit out Project Specifications Construction - demo and replace all interior finishes including ceilings, walls and carpets. Install 3 new Application Labs. Install Security and Fire systems to company specifications. Install data center. Furniture - install 100 Herman Miller cubicles and 125 Teknion cubicles. Upgrade all lobby furniture. Fitout building with various lunch room, training room and boardroom upgrades
|
||||||